Moonlight Lower
Bridge

Project
Highlights

The bridges were installed to connect the Holy Grail Ski Trail from Ulery’s Lodge to the Madison Village in Moonlight Basin.

Project consisted of two bridges, being Upper and Lower.

Upper Bridge Approx. 170’ in length Lower Bridge Approx. 280’ in length.
Project Facts
Completed: November 2020
Project Budget: $1.7 Million
Length: 170 ft Upper Bridge - 280 ft Lower Bridge
Sustainable
Features
18” concrete spread footings
36” diameter concrete abutments and piers
Corten steel superstructure and handrailing
Testimonials
No project has meant so much to so many people…all was handled with the utmost professionalism and respect for the environment and the historic structure.
Glacier National Park Volunteer Associates
The key attributes of the Dick Anderson team are their capabilities, work effort, and ability to manage.
Danny Kaluza — Director of Support Services
The quality of … work was excellent, and they expected and obtained high-quality work from their subcontractors.
Jim Beal — CTA Principal in Charge / Sheridan College Projects
Related Projects
Let's get
to work
The team at Dick Anderson Construction has never been stronger, and we bring our exceptional skills, experience and commitment to quality to every project. Though our talented employees come from diverse educational and technical backgrounds, they share common traits – working hard to meet or exceed client expectations, paying attention to detail, and showing integrity in all they do. That’s The DAC Way.